Foundations of Systems Analysis - ITFN 1112
Team Semester Project (Fall 2004)
Purpose: To gain an understanding of the systems analyst approach to solving business problems in a hands on project with a focus on the planning phase of systems analysis with emphasis on traditional and object oriented processes.
Facts About the Project:
Project Title: Yo-Yo Manufacturing Company System
System Description:
Problem Defined:
More modern manufacturing companies have their own web sites that display their products for sale in addition to using mail order catalogs. This competition is eating into the profits of Yo-Yo manufacturing because potential customers are accessing individual manufacturing companies’ web sites before looking at the catalogs. Therefore, Yo-Yo Manufacturing has decided that they need to furnish pictures of the machine parts they have for sale in a database that will be accessed via their own web site. In addition, the web site will allow you to contact Yo-Yo manufacturing directly to ask questions.
Assumptions:
Deliverables for this project:
General Notes:
· All work should be done on the laptop using word, no hand written documents. A narrative that explains your diagrams and assumptions should accompany diagrams.
Deliverables:
Timetable:
|
Deliverable Number |
Description |
Date Due: |
|
1 |
Team Mission Statement |
September 23th, 2004 |
|
2 |
Cost Benefits Analysis Table |
September 23st, 2004 |
|
3 |
Context Diagram |
September 28th, 2004 |
|
4 |
DFD Diagram |
October 5th, 2004 |
|
5 |
Entity Relationship Diagram (ERD) |
October 12th, 2004 |
|
6 |
Structure Chart |
October 19th, 2004 |
|
7 |
Events Table |
October 26th, 2004 |
|
8 |
Class Diagram |
November 2nd, 2004 |
|
9 |
Use Case Diagrams |
November 9th, 2004 |
|
10 |
Application Architecture Plan |
November 16th, 2004 |
|
11 |
Time table for Yo-Yo’s Architecture Plan |
November 23rd, 2004 |
|
12 |
Implementation & Support Plan |
December 7th, 2004 |